You are here: Home » Projects » Steel Fabrication and Export Packing for a Nigerian Pharmaceutical Plant

Steel Fabrication and Export Packing for a Nigerian Pharmaceutical Plant

For a pharmaceutical plant project in Nigeria, ZSJH coordinated drawing design and detailing with steel component fabrication and shipment preparation. The factory videos capture the physical delivery package: fabricated beams, drilled end plates, stacked members and strapped bundles. These are the components that must be matched to drawings and packing documents before overseas assembly.

The project’s design and detailing stage took 10 days, followed by approximately 40 days from fabrication to dispatch. The timings describe this project; other orders require a schedule based on their own drawings, quantities and delivery requirements.

Delivery Package

Parameter

Details

Project

Pharmaceutical factory prefabricated steel structure

Location

Nigeria

Scope

Drawing design and detailing, fabrication, packing and dispatch preparation

Grid dimensions

69.94 m × 44.96 m

Transverse grid spacings

11.21 m / 22.50 m / 11.25 m

Main steel grades

Q355B and Q235B

Main components

Steel columns, roof beams, Z purlins, bracing and steel stairs

Schedule net weight

Approximately 66.57 t

Schedule quantity

3,107 assemblies and listed items

Design and detailing

10 days for this project

Fabrication to dispatch

Approximately 40 days for this project

Weight and quantity refer to the supplied component schedule; final delivery follows the approved packing list. Lead times vary by project.

Connecting Drawings to Fabricated Members

The project’s Tekla and IFC files describe a steel frame covering a grid envelope of 69.94 m by 44.96 m. Column and roof framing layouts establish where the primary members sit, while purlin and bracing layouts define the secondary steelwork. For a fabrication package, these relationships need to remain traceable when members move from drawings to the shop floor.

The component schedule records a net weight of approximately 66.57 tonnes across 3,107 assemblies and listed items. The schedule provides a reference for organizing the fabrication package, while the approved bill of materials and packing list define the final delivery quantities.

The steel model provides the structural reference for coordinating the factory building with its planned internal layout and equipment requirements.

Nigeria pharmaceutical plant roof steel framing model.jpg

Image 1 Nigeria pharmaceutical plant roof steel framing model

Nigeria pharmaceutical plant roof framing layout drawing.jpg

Image 2 Nigeria pharmaceutical plant roof framing layout drawing

What the Factory Footage Shows

The videos show long steel members with welded plates, bolt-hole patterns at connection ends and components positioned in stacks. Some clips show individual fabrication details, while others show groups of members prepared together. These views make the scale and form of the prefabricated package easier to understand than a component list alone.

The principal materials identified in the project files are Q355B and Q235B. Primary steelwork includes H-section columns and roof beam assemblies. Secondary steelwork includes Z-section purlins, tie members, roof bracing, knee braces and stair components. Fabrication details and packing arrangements are coordinated with the component geometry and project delivery requirements. 

Nigeria pharmaceutical plant steel beam fabrication details.jpg

Image 3 Nigeria pharmaceutical plant steel beam fabrication details

Bundling and Shipment Preparation

Several clips show members grouped into bundles and held with straps, with spacing or protective pieces visible between some members. Bundling gives the delivery team a practical way to handle groups of components, but the arrangement must also suit their dimensions, the transport plan and safe unloading at destination.

For a comparable export order, the packing plan should coordinate component marks, bundle references and the packing list. Small connecting items need an identified packing location, and handling arrangements should be agreed before dispatch. Agreeing these details before dispatch helps the receiving team prepare for unloading and component identification.

The accompanying model and layout images provide a useful reference for understanding how the bundled steelwork relates to the overall structure.

Nigeria pharmaceutical plant bundled prefabricated steel components.jpg

Image 4 Nigeria pharmaceutical plant bundled prefabricated steel components

Nigeria pharmaceutical plant steel components prepared for dispatch.jpg

Image 5 Nigeria pharmaceutical plant steel components prepared for dispatch

Discuss Your Export Steel Package

Contractors and project buyers can begin with approved structural drawings, available CAD or BIM files, a bill of materials and the required delivery destination. Where drawings are incomplete, the design and detailing scope should be agreed before the fabrication programme is fixed.

Send your drawings and delivery requirements to sales@zsjhsteelgroup.com. ZSJH can discuss the required steel components, fabrication scope, packing arrangements and a schedule suited to your pharmaceutical or industrial building project.