Steel Fabrication and Dispatch for a 5,500 m² Thailand Chemical Platform

A project delivered through connected stages

For a chemical equipment platform project in Thailand, ZSJH participated from drawing design through project dispatch. This case focuses on the practical link between fabrication and export preparation: turning detailed steel components into identifiable, handled and transportable items for an overseas project.

thailand-chemical-equipment-platform-tekla-overall-model.png

Image1 Thailand Chemical Equipment Platform – Tekla Overall Model

Project parameters

Item

Value

Project location

Thailand

Project use

Chemical equipment platform and associated pipe rack

Building area

5,500 m²

Drawing design

5 days

Steel detailing

7 days

Dispatch date

27 October 2026

Project duration

Approximately 3 months

ZSJH scope

Drawing design, detailing, steel fabrication and project dispatch

Main components in reviewed model

H-section columns, primary and secondary beams, plates and connection components

Principal steel grades in reviewed model

Q355B and Q235B

Platform elevations in reviewed model

+2.500 m, +6.000 m, +11.000 m, +16.000 m and +19.000 m

Fabrication built around component interfaces

Workshop photographs show fabricated members with end plates, base plates and welded stiffeners. These interfaces require the workshop to work from the relevant component drawings rather than treat each section as an isolated length of steel.

Visible progress from fabrication to coating

The supplied photographs document steelwork at different stages. Uncoated members reveal plate arrangements and connection details, while coated columns and beams show the components after a later surface treatment stage. The coated parts retain visible bolt holes and identification labels. Coating appearance alone does not establish a paint chemistry, dry film thickness or corrosion category, so this case makes no unsupported specification claims.

coated-platform-steelwork-stacked-for-thailand-dispatch.jpg

Image 2 Coated Platform Steelwork Prepared for Dispatch

Preparing mixed steelwork for shipment

Industrial platforms include long members alongside smaller connection parts and access components. Their different shapes make shipment preparation part of the fabrication planning discussion. The project photos show stacked steelwork with separation materials and restraints, as well as a banner identifying dispatch to Thailand. Keeping component references connected with delivery records supports checking and receipt at the next stage.

zsjh-steel-structure-dispatch-to-thailand-banner.jpg

Image 3 ZSJH Steel Structure Dispatch to Thailand

Export coordination through the dispatch milestone

Container trucks photographed at the factory provide a record of the outbound logistics stage. ZSJH’s confirmed scope extended from drawing design to project dispatch, giving the customer a connected point of coordination across engineering and manufacturing. Shipment is a defined project milestone; arrival, erection and commissioning remain separate stages. No shipment duration, container count or final project tonnage is asserted here.

container-truck-at-zsjh-factory-for-project-dispatch.jpg

Image 4 Coated Platform Steelwork Prepared for Dispatch

Request a fabrication and export proposal

Looking for a supplier for an overseas industrial steel platform? Share your drawings, component list, required delivery batches and destination with ZSJH. We can discuss fabrication, surface treatment and export preparation against the scope and technical requirements of your project.

Quick Links

Product Category

Other Links

Contact Us
Contact Us
Copyright © 2026 Zhong Sheng Jia He Steel Structure (Tianjin) Co., Ltd. All Rights Reserved.