Steel structure construction requires strict control over material quality, installation accuracy, welding quality, lifting operations, temporary fixing, electrical safety, and final inspection. Following standardized construction procedures can effectively improve structural safety, project quality, and long-term service performance.
Core materials for steel structures, including steel plates, high-strength bolts, and welding consumables, must be inspected before entering the construction site. All materials should be delivered with valid quality certificates, such as steel mill certificates and bolt torque inspection reports.
After arrival, materials should be sampled and tested according to project specifications. Steel materials must be checked to ensure that thickness, section dimensions, and specifications match the design requirements. The surface should be free from serious corrosion, cracks, and visible defects. Mechanical properties such as tensile strength and yield strength should comply with GB/T 700 or relevant standards.
High-strength bolts should be inspected for torque coefficient and anti-slip coefficient. The torque coefficient deviation should be controlled within ±10%, and the anti-slip coefficient should meet the design requirements, generally not less than 0.45 for friction-type connections.
Welding materials must match the base steel. For example, E50 series electrodes are commonly used for Q355 steel. Incorrect welding materials may reduce weld strength and affect structural safety. Unqualified materials must be stored separately, clearly marked, and prohibited from entering the construction process.
More than 80% of steel structure installation work involves high-altitude operations. Therefore, comprehensive fall protection measures must be implemented.
Workers must wear double-hook safety harnesses. The harness should be used correctly, with the hook fixed to a stable steel structure node instead of temporary supports. Anti-slip safety shoes should also be worn to improve grip and reduce the risk of slipping.
Temporary working platforms, such as steel scaffolding and working boards, should be firmly fixed before high-altitude installation. Guardrails should be installed, with a recommended height of not less than 1.2 meters. Walking on unfixed steel components is strictly prohibited.
Edge protection must be provided around structural edges and reserved openings. Guardrails and dense-mesh safety nets should be installed to prevent workers, tools, or materials from falling.
Welding is one of the most critical processes affecting the load-bearing capacity of steel structures. Both welder qualification and weld inspection must be strictly controlled.
Welders must hold valid special operation certificates suitable for the required welding method, such as manual arc welding or submerged arc welding. Unlicensed welding operations are strictly prohibited.
Key welds, such as beam-column joints and crane beam splice welds, should be inspected using non-destructive testing methods, including ultrasonic testing or magnetic particle testing. The inspection ratio should meet design and specification requirements. Important welds may require 100% inspection, and the inspection results should comply with GB 50205 or relevant acceptance standards.
Before welding, grooves must be cleaned to remove oil, rust, and other impurities. Groove angle and gap should meet design requirements. After welding, slag should be removed in time, and the weld surface should be checked for defects such as pores, welding lumps, incomplete penetration, and cracks.
Steel components such as steel beams and steel columns are usually heavy, and lifting operations must be carried out in strict accordance with safety regulations.
The rated lifting capacity of the crane should be at least 1.2 times the weight of the component. For example, a 5-ton component should be lifted with a crane rated at 6 tons or above. Lifting tools such as wire ropes and shackles must be checked before use, and overload lifting is strictly prohibited.
Lifting points should be set according to the component design. If no lifting point is specified, the center of gravity should be calculated, and lifting points should be arranged symmetrically to prevent tilting. Long and slender components should not be lifted from a single point to avoid bending deformation.
A qualified lifting commander should be assigned on site. Standard signals, such as flag signals or intercom communication, should be used. Workers are strictly prohibited from standing within the lifting radius. When the component is lifted about 50 cm above the ground, lifting should be paused to check the lifting tools and component balance before continuing.
Installation accuracy directly affects the stability and safety of steel structures. Professional measuring instruments should be used throughout the installation process.
The axis position of steel beams should be measured using a total station. The allowable deviation should generally be controlled within 3 mm for single-story steel structures and within 5 mm for multi-story steel structures. Each steel beam should be checked after installation to avoid cumulative errors.
Component elevation should be measured with a level instrument. The deviation should generally be controlled within ±3 mm. For steel columns, welding shrinkage should be considered, and a shrinkage allowance of 2–3 mm may be reserved according to the project situation.
The verticality of steel columns should also be checked carefully. The verticality deviation of each column should generally not exceed H/1000, where H refers to the column height. If the deviation exceeds the allowable range, it should be adjusted with proper tools such as jacks. Forced installation is not allowed.
Before permanent fixing is completed, steel components must be temporarily secured to prevent instability or collapse.
Steel columns may be temporarily fixed with guy ropes or temporary supports. Steel wire ropes with suitable strength should be arranged symmetrically to keep the column stable and prevent tilting.
Steel beams should be temporarily fixed with welding points or bolts before final connection. Temporary welds should meet basic strength requirements, and each end should be fixed with enough high-strength bolts when bolted connections are used.
If installation work must stop due to extreme weather, such as strong wind, the already installed components should be reinforced with additional temporary supports or guy ropes to prevent imbalance or collapse.
Steel structure installation requires many electrical devices, including welding machines, cranes, and cutting machines. Temporary power use on site must comply with electrical safety requirements.
A standard temporary power distribution system should be adopted. Each electrical device should have an independent switch and leakage protection device. Leakage protectors should have a rated action current of no more than 30 mA and an action time of no more than 0.1 seconds.
Cables should be protected by overhead installation or underground conduits. Underground cables should be buried at a safe depth to avoid damage from rolling or impact. For high-altitude work, cables should be fixed with insulated hooks and kept away from steel components to reduce electric shock risks.
Metal equipment such as cranes and working platforms should be properly grounded. The grounding resistance should meet safety requirements. Welding machine secondary cables should be well insulated and should not directly contact steel structures to avoid accidental current paths.
High-strength bolts are key connection components in steel structures. Bolt installation should generally be completed in two steps: initial tightening and final tightening.
During initial tightening, bolts should be tightened to about 60%–80% of the required pretension force using a torque wrench. After initial tightening, marks should be made to prevent missing bolts.
Final tightening should normally be completed within 24 hours after initial tightening. The final torque should be determined according to the design requirements or relevant specifications. After final tightening, the exposed thread length should usually be 2–3 threads, with no broken threads or visible defects.
After completion, torque inspection should be carried out by sampling. The sampling ratio is generally 10%, and not less than three sets should be checked. The torque deviation should be controlled within ±10%. Any bolts that fail inspection should be re-tightened and recorded.
Steel structure installation is sensitive to weather conditions. Construction plans should be adjusted according to wind, rain, snow, and temperature.
When the wind force reaches Grade 6 or above, high-altitude operations and lifting work should be stopped. Installed components should be checked and temporarily reinforced if necessary.
Welding should not be carried out in rainy weather, as moisture may cause pores and other weld defects. After snow, snow and ice on the component surface should be removed before construction. Water washing should be avoided to prevent freezing and installation deviation.
During high-temperature weather above 35°C, high-altitude work during the hottest period of the day should be avoided. Drinking water, heatstroke prevention supplies, and proper ventilation should be provided. Welding areas should also be ventilated to reduce the risk of welding fume exposure.
Finished product protection and final inspection are essential to ensure project quality before handover.
After installation, steel components should be protected from impact, scratches, and deformation. During crane operation, contact with installed steel members should be avoided. Anti-corrosion coatings, fireproof coatings, and paint should be applied after installation acceptance. Before coating, the component surface should be cleaned to remove oil, dust, and other contaminants.
Before project completion, a comprehensive inspection should be carried out. Inspection items should include weld appearance, bolt exposed threads, component verticality, installation accuracy, and coating condition. For large-span steel structures, deflection inspection should be conducted according to design and specification requirements.
All quality documents should be collected and archived, including material re-inspection reports, welding inspection reports, high-strength bolt tightening records, and construction acceptance documents. Complete documentation ensures traceability and provides reliable reference for future maintenance.
Steel structure construction requires strict control of both quality and safety. From material inspection and welding quality to lifting operations, bolt tightening, temporary fixing, and final acceptance, every step directly affects the safety and durability of the project.
By following standardized construction procedures and strict inspection requirements, steel structure projects can achieve higher installation accuracy, stronger structural performance, and longer service life.